Search

Short-term Closure of Brock St. W. Beginning April 6th

Posted on Tuesday, March 30, 2021 01:37 PM

A portion of Brock St. W. will be closed to through-traffic, from Tuesday, April 6th for several days. The road will be closed between Toronto St. and Bascom St. The closure is related to Brock Street Culvert Project construction work. Centennial Dr. will remain closed at the same time. The duration of the closure is weather dependent.

The large crane will move into position on Brock St. and will be used to install pre-cast culvert sections immediately south of Brock St. Once the segments are in...

Culvert Construction Activity To Continue on Family Day

Posted on Friday, February 12, 2021 03:34 PM

Culvert Connection Logo 

For immediate release
Portion of Parking Lot Behind Library to be Temporarily Closed

The contractor will be working at the culvert construction site south of Brock St. during the day on the Family Day holiday (Monday, Feb. 15th) to position equipment and prepare the heavy crane to work at the site.

A portion of the parking lot behind the Library will also be temporarily closed to enable construction equipment to safely maneuver into position.

Pre-cast culvert sections will be installed...

Culvert Construction Paused While Engineering Study Completed

Posted on Wednesday, November 11, 2020 01:34 PM

Uxbridge Brock Street Culvert Logo

November 11, 2020

Brennan Paving and Construction has temporarily paused active construction on the installation of culverts south of Brock St. to check the impact of construction on adjacent buildings.

The Township of Uxbridge has requested additional engineering reports to better understand the situation. Obtaining updated data and information is often a necessary step in a construction project.

It is not been determined what impact the work interruption will have on the overall project schedule.

Brock St. W. Reopens to Pedestrian and Vehicle Traffic

Posted on Friday, October 30, 2020 04:17 PM

Sidewalk on north side of street open for pedestrians 

Replacement of the Brock St. culvert underneath Brock St. W. is now complete and the road will reopen at 6:00pm on Friday, Oct. 30th. The sidewalk on the north side of the street is also open. Construction to replace the culvert continues south of Brock St. and Centennial Dr. remains closed until the end of the year.

Construction crews have paved the parking area north of Brock St. but that area will remain closed to the public as it is...

Culvert Construction To Continue on Saturday October 24th

Posted on Tuesday, October 20, 2020 08:12 AM

Work is weather dependent

Construction crews will be working on Saturday Oct 24th in Downtown Uxbridge on the Brock St. Culvert project weather permitting.

For additional information on the Brock Street Culvert Project, please visit www.uxbridgeculvert.ca.

Contact Us